Due to the heavy rains, we lost the weekend schedule in setting and pouring concrete sidewalks around Amos Eaton and Lally, but we were able to get the hole backfilled in the location of the tank (they were working on grading that road and plaza this morning). The main doors of AE and the sidewalk around the south side should be reopened by tomorrow (they were pouring concrete this morning). The pathway leading up to the SW basement exit should be in by Wednesday , and the SE entrance by end of week. We should have a path through the Quad by mid to end of week (If not sooner). Irrigation systems, plantings, trees and sod should continue through the week. New site lights are scheduled to be installed around 12/1.
Posted under Uncategorized by Duane DeWeerdt 15.11.2009
Comments Off
|
BUILDINGS AFFECTED:
|
Cogswell, Polymer, MRC
|
| |
|
|
|
SYSTEMS AFFECTED:
|
Air Supply and Fume Exhaust
|
| |
|
|
|
DATE WORK TO BE DONE:
|
Wednesday November 18th
|
| |
|
|
|
LENGTH OF TIME REQUIRED:
|
8:00 AM to Noon
|
| |
|
|
|
REASON FOR SHUTDOWN OR REPAIR:
|
Drain coils
|
Posted under Regularly Scheduled Shutdown, shutdown by Duane DeWeerdt 10.11.2009
Comments Off
The planting plan for the project was recently released and can be found here
science-quad-north-planting-plan
Posted under Informational by Duane DeWeerdt 26.10.2009
Comments Off
To: Campus Community
October 2, 1009
On October 2, 2009, construction will begin in the quadrangle area between the Voorhees Computing Center and the Greene building, to improve the traffic patterns, paving and landscape. The fenced area and re-routed traffic patterns are illustrated on the plan below. This construction is expected to continue into November. If you have questions or concerns, please contact:
Oleh Turczak
276-4244
Turczo@rpi.edu
Science Quad North Traffic Pattern
Posted under Uncategorized by Duane DeWeerdt 01.10.2009
No comment »

When completed this area will mirror the landscape of the quad south of VCC. Components of the work will include.
-
New concrete sidewalks and lighting for improved pedestrian safety.
-
Necessary repairs to underground utilities.
-
Removal of failing trees and planting of more sustainable high canopy trees.
-
Installation of lighting, benches and bicycle racks.
-
Improved access for emergency, delivery and service vehicles.
Posted under Informational by Duane DeWeerdt 27.09.2009
Comments Off

The Physical Plant will be making repairs to the cornices of the 87 Gym. Scaffolding has been erected over the stairs next to the 87 Gym to protect pedestrians during the work.
Posted under Informational by Duane DeWeerdt 09.03.2009
Comments Off
In order to perform preventative maintanence on our building systems the Physical Plant has implemented reqularly scheduled shutdowns. When planning your experiments please keep these in mind.
For further information click on the Regularly Scheduled Shutdown page or click here
Posted under Regularly Scheduled Shutdown, shutdown by Duane DeWeerdt 19.02.2009
Comments Off